|
Most of the money to pay for Warren's new parking
garage should be on the way within the next ten days.
Pennsylvania Gov. Ed Rendell pledged the $7.95 million
to pay for the parking garage last year, but so far
the money has remained in Harrisburg.
The delay caused the city to seek financing from a bank
to pay for the ongoing construction.
But Warren Mayor Mark Phillips said Thursday that he
expects the bulk of the money should be on the way to
Warren within seven to ten days.
The $5.2 million represents the first installment of
the state funding, said Phillips.
The remainder, said Phillips, could "potentially
be received very soon thereafter."
Phillips said on Thursday, "As of this point we
have yet to receive any of the grant money promised
to us by the state."
The process of obtaining the funds, said Phillips,
has been a "cumbersome, long process."
Included in the process, he said, have been visits
from state personnel to verify that Warren has sources
of required matching funds in connection with the "Impact
Warren" project.
Phillips said architects had to isolate costs paid
by Northwest Savings Bank as matching private funds
"to satisfy inspectors."
That process included real estate costs Northwest incurred
in acquiring properties for the parking garage on Clark
St.
Those real estate appraisals were forwarded to the
state at the beginning of last week, said Phillips.
As a result, the mayor said, "We hope to realize
$5.2 million within seven to ten days."
Phillips said that while the city did incur some costs
in financing the construction while the state funds
were being awaited, he did not immediately have an estimate
of those costs.
But Phillips said the city was able to collect some
rent on the Northwest Savings Operations Center, which
is located on the western end of the project area, during
the delay and the those revenues have exceeded the interest
costs on the financing for the parking garage.
Balancing the rent collected against the interest charges,
said Phillips, "There was a net gain."
"Of that 20,000, the part in the basement has
garnered the most interest," Phillips said.
The developer has said that one of the city's two senior
centers is interested in locating in the Allegheny Point
building. Phillips also pointed out that an organization
providing care for the elderly has expressed interest
in the spot as well. "And there are a couple of
others I'm not privy to," he said.
There has also been interest in the building's space
on the street level, according to Phillips.
In the Liberty West building, there is also 10,000
square feet at street level and 10,000 square feet at
the basement level available. "We now know about
half of the street level and the basement will be occupied
by County National Bank," Phillips said.
The bank plans to operate drive-through banking services
on the lower level, according to Phillips.
Looking at the Impact Warren available space overall,
Phillips said, "It's fair to say about half the
space has very high interest or has been spoken for
with commitments."
Phillips also said that the Main Street Program "continues
to seek out any and all retailers that might want to
come to the area, that aren't here already, and existing
retailers" seeking to expand.
Both the developer and the Main Street Program, Phillips
said, "have a vested interest in diversifying the
downtown area."
Some retailers have shown interest in the buildings,
according to developer Bob Yoder. "We have a couple
that we're working with," he said. Yoder declined
to name the interested retailers.
He also said the available space is about 70 percent
filled at this point.
"It's moving along like I had hoped," Yoder
said.
|