|
Bridge or no bridge, construction of riverfront townhouses
in downtown Warren could still get underway this fall.
The original plan was to hold off on construction of
the 30 townhouses until construction of the new Hickory
Street Bridge was completed in November. The area of
the "Island" Parking Lot where the townhouses will be
constructed is being used as a staging area for bridge
construction.
However, PennDOT now says that weather and high river
levels this summer have resulted in unavoidable delays
and the bridge will not be completed until at least
next spring.
But Warren Mayor Mark Phillips said the delay in building
the bridge will not necessarily result in a set-back
in the timetable for construction of the riverfront
townhouses.
Phillips admitted when he first learned of the delay
in building the bridge, "We had thought that," meaning
he thought building of the townhouses would also be
delayed.
But the situation has been discussed with PennDOT, said
the mayor, and he has been assured "all the materials
and supplies they are storing in the area will be completely
used or relocated this fall."
Once the bridge construction materials are removed from
the parking lot, said Phillips, "We'll have the opportunity
to start the townhouses." "Weather permitting," said
Phillips, "there is still an opportunity to start on
the townhouses this fall."
Each townhouse will have two or three upstairs bedrooms
with garden flats on the first floor. Each townhouse
will have a porch and a balcony with views of both the
Allegheny River and downtown Warren. Each tenant will
have at least one parking space beside the townhouse
and one in the parking garage.
In another matter related to "Impact Warren" -the $50
million downtown revitalization project - Phillips said
he expects demolition of three vacant houses across
Clark St. from Loranger Manufacturing will take place
within the next three weeks.
Demolition of the three houses, said Phillips, will
allow Perry Construction, the contractor for the new
five-level, 630-space parking garage, to move construction
equipment into the area.
The contractor is currently doing preliminary work and
surveying the "footprint" for the parking garage. Motorists
who have parked in the vicinity of the Northwest Savings
Operations Center at the foot of Liberty St. are also
being advised they need to relocate their vehicles,
said Phillips.
To help replace some of the parking spots lost to construction
activity, Phillips said the city has established a temporary
parking lot just south of Langdon Dr.
|