|
Back to the drawing board.
Tests on the site of where Warren's new five-level parking
garage will be built fell just short of ideal, which will
require some redesigning of the facility.
But the 600-plus space garage remains on schedule
for completion late this year.
Warren City Council member David See said that the
test results should not be viewed in any way as being
a "setback" for the $8.2 million component of
"Impact Warren."
"Now we know what we need to do" in terms
of designing the garage on Clark St., said See.
Grout Systems, Inc. of Ohio last week drove a pile
to a depth of 40 feet to determine the subsurface composition
and what will need to be done to support the parking
garage.
Dense gravel was found at 40 feet. Weight was then
added and the testing mechanism finally failed at 180
tons.
If failure had taken place at 200 tons, rather than
180 tons, said See, the garage could have been designed
and constructed with fewer columns.
See said that even with the one column design, the
garage would have had a "2 X" safety factor,
meaning each column could support twice the amount of
weight actually placed on each column.
"'How many columns do we need?' is the question
we were trying to answer and now we have our answer,"
said See. "It's just a matter of how we build it.
We always knew we could put a garage there."
Based on the test results, the parking garage is now
being redesigned by Tom Harley Architects, Indiana,
Pa.
The testing was required before the parking garage
could be advertised for construction bids, said See.
"Now we can bid to an exact design load rather
than putting it out to bid before knowing," said
See. "The test was just short of what we had hoped
for, but it's not a setback at all."
More columns will mean the parking garage will be
more expensive, said See, but the additional cost will
not be known until after the facility is redesigned
and bids are received.
Gov. Ed Rendell has pledged the entire $8.2 million
needed for the parking garage, which will more than
replace parking spaces lost due to "Impact Warren"
construction in what is now the Island Parking Lot.
The governor has already provided $3.2 million and the
$5 million balance will be included in a state bond
issue which has to be approved by state lawmakers.
See said the all-steel garage should be under construction
by April and should be completed by the end of 2004,
possibly as early as November.
The garage will be almost identical to the parking
garage recently opened in Meadville, said See.
|